Information on Sussex
Brighton 'B' Power Station - Page 2
CIVIL WORKS
The strata of the site consist of gravel and sand and a lignite formation
known locally as "Stromboli" which was found generally on the site at about
35 to 50 ft. below the surface level; beneath this is a load-bearing layer
of clay and chalk.
The basement floor was supported on groups of reinforced concrete piles
which went down to varying depths of 35 to 50 ft. each designed to carry
loads of 60 to 70 tons. Difficulties were encountered in penetrating the
"Stromboli" owing to its resilience during pile-driving; in one instance
10,000 blows using a 2.5 to 3 ton ram were required to penetrate this stratum.
About 6,000 piles were driven for the complete building.
About l5 million bricks were used in the complete structure. The silver
grey and bronze facing bricks were obtained from the High Broom Brick and
Tile Company of Tunbridge Wells. They were specially selected by the architect
to blend with the natural tones of the surrounding beach.
The Turbine Room, including loading bays, is 850 ft. long, 60 ft. wide and
81 ft. 6 in. high.
The Boiler House, including workshops, is 900 ft. long, 100 ft. wide and
1 15 ft, high.
The Chimneys are 350 ft. high with an inside diameter of 32 ft. at base
and 24 ft. at the top.
The Cable Tunnel under Shoreham Harbour is 90 ft. below ground and the internal
diameter is 10 ft.

Each turbine consisted of a high-pressure, intermediate and low-pressure
cylinder in which the steam expands, driving a bladed rotor.
SHOREHAM HARBOUR
At the project stage of "B" Station it was clear that the existing Harbour
would not be able to cope with the traffic that would be needed to carry
the 850,000 tons of coal per annum required for both "A" and "B" Stations.
At first it was considered that the Harbour should be improved to accommodate
vessels up to 2,650 tons but after further consideration it was decided
to amend the plans to admit vessels up to 4,500 tons.

All generators were operated from a control room where instruments indicate
station output and local grid conditions. Agreement was reached with the
Harbour Trustees and the work of enlarging and improving the Harbour was
authorised by the Shoreham Harbour Act 1949. This work, carried out by Sir
Wm. Halcrow and Partners on behalf of the Central Electricity Authority,
was begun on 1st January 1954 and completed in 1957.
The ability of Shoreham to accept larger vessels has led to its rapid
development as a general cargo port in later years.

P.F.Mills. Spare Grinding balls in the foreground
Previous Page Next
Page
Top of Page main
page: www.yeoldesussexpages.com
Shoreham Power Station
